Wigton’s 70 MW Solar Plan Waits on an Unsigned JPS Power Purchase Agreement

Wigton Energy says it cannot raise the money to build 70.53 megawatts of new solar until Jamaica Public Service (JPS) signs a power purchase agreement with it. At the company’s annual general meeting, chairman Dan Theoc told shareholders that Wigton has met JPS and the Office of Utilities Regulation (OUR) and written to the energy minister about the delay, the Jamaica Observer reported on 23 October 2026.

Asked whether the projects were effectively at a standstill, Theoc said: “We cannot secure financing without an executed power purchase agreement.”

What is held up

  • Two solar farms. Wigton has leased land for two developments, described at the meeting as about 50 MW and 20 MW. Its September interim report puts their combined capacity at 70.53 MW. That is more than the 62.7 MW of wind generation the company runs today.
  • A 20-year contract. JPS would buy the electricity under a proposed 20-year agreement. The terms have to work for Wigton and for the lenders expected to fund construction.
  • A year at the regulator. The Observer’s BusinessWeek reported in October 2025 that the agreement had been completed and sent to the OUR for review. A year later, the terms are still unresolved.
  • Unnamed sticking points. Chief executive Gary Barrow said there are “a few problematic provisions” still being worked through. The provisions were not identified. Barrow said Wigton would not “expedite and compromise”, but still aims to break ground within six months.
  • Not just Wigton. Wigton said it understood the other winning bidder from the same procurement round is also waiting for an agreement before it can arrange financing. The Gleaner has reported that the Generation Procurement Entity (GPE) awarded about 100 MW of solar contracts to Wigton and Sunterra Energy Jamaica in November 2024.

Shareholders were told the difficulty “may or may not be related to the fact that JPS itself is going through a very dynamic time”. Theoc said the talks are between Wigton and JPS, with the OUR also taking part.

The money waiting to be spent

Wigton says it plans to spend at least J$8 billion over the next two years. It held J$3.26 billion in cash and cash equivalents at 30 September, after fully repaying its Bond A that month. It is negotiating terms on its remaining Bond B, which has a principal balance of about J$1.9 billion and falls due within 12 months.

The wind business is producing more. Output rose 16.6 per cent to 94.7 million kilowatt-hours in the six months to September, and electricity sales rose 13.6 per cent to J$1.51 billion. Net profit for the half-year still fell 11.5 per cent to J$313.6 million, mainly because of lower insurance and foreign-exchange income and hurricane repair costs.

Separately, Wigton says it is in advanced talks on a solar project with a major Jamaican industrial company, which it did not name. Its pipeline for commercial and industrial customers includes 10 MW it could deliver over the next two to three years. It has also been shortlisted for upcoming regional tenders elsewhere in the Caribbean.

Why the wider grid is watching

Jamaica’s policy is to get half its electricity from renewable sources by 2030. A report by the energy think tank Ember, covered by the Observer on 4 October, put the renewable share at 8.9 per cent in 2024. The next big step is the GPE’s auction for up to 300 MW of renewable generation and 150 MW of battery storage, which the agency expects to open before the end of the year. We set out that timeline in our earlier post on the 300 MW auction.

What this means. Winning a government power tender does not get a solar farm built. Lenders need a signed power purchase agreement with JPS first, and both winners from the November 2024 round are still waiting for one almost two years later. Anyone counting on the 300 MW auction to add clean power quickly should treat contract signing as a separate, slow step, not a formality.

What to do. If your business supplies or installs for utility-scale solar, do not plan work around Wigton’s six-month groundbreaking target until it announces a signed agreement. If you intend to bid in the 300 MW auction, read the draft power purchase agreement in the tender pack closely when it is published, and build the time it takes to finalise those terms into your financing plan.

Last fact-checked: 26 October 2026.